pmp pmi-001 braindumps (1)
- Tuesday, July 14, 2009, 22:55
- Cert Tests
- 1,410 views
- Add a comment
Exam Name: Project Management Professional
Exam Type: PMI
Exam Code: PMI-001 Total Questions: 980A benefit-cost ratio of 3.22 indicates a:
To help you take your PMP exam we have compiled a collection of braindumps, these have been supplied by our members and we have also scoured the internet for PMP braindumps
Simply choose the relevant PMP braindump below to download, click the radio button next to it and click on the Download braindump button
All of our PMP braindumps are supplied by our members and are frequently updated with latest versions
PMP Braindumps for PMP Certification candidates at Trandumpers PMP Section.
Have you checked our Online testing section to see if we have any PMP online tests ?
A. Profit of s3.22 per unit produced.
B. Profit of s3.22 for each dollar expended.
C. Resources assigned to other tasks on the critical path.
D. Payback of s3.22 for each dollar expended.
During project lose-out, the final task is to….
A. Verify that contractual obligations were met.
B. Transfer the deliverables to the client.
C. Reassign team member.
D. Complete performance/lessons-learned records.
Answer: B
You are the project manager. Which of the following would be required to ascertain what impact a
change would have on the project in a situation where a customer requests a scope change in
the project? Note: you already have the work breakdown structure, change request and scope
management plan.
A. A histogram
B. A responsibility matrix.
C. Performance reports.
D. A Monte Carlo simulation.
E. A Pareto diagram
Answer: C
Which of the following is NOT an essential regarding a project close-out?
A. Documenting formal acceptance of the product.
B. Documenting the final risk assessment.
C. Documenting the lessons learned.
D. Documenting the final project scope
E. None of the above.
Answer: B
Which of the following is neither a tool nor a technique for source selection?
A. Independent estimates.
B. A weighting system.
C. A screening system.
D. Organizational policies
E. None of the above.
Answer: D
Bar charts generally illustrate:
A. Progress of status.
B. The critical path.
C. Budget relation ships.
D. Logical relationships.
Answer: A
The critical path needs to be reduced by 25%. All of the following actions are relevant to
accomplishing this objective EXCEPT:
A. Adding resources.
B. Eliminating float.
C. Crashing time schedule.
E. Paralleling activities.
E. All of the above.
Answer: B
The cost-effective rule for shortening a project is to crash the:
A. Critical tasks.
B. Non-critical tasks.
C. Tasks with lowest cost.
D. Tasks with highest cost.
Answer: A
High quality IT Certification Training Exam Questions, Study Guides and Practice Tests are in Downloadable PassGuide Testing Engine,Successful for IT Certification or Full Refund for you.Contact Us:Sales@PassGuide.com|
Type |
Exam Bible | New Questions & Answers |
Latest Updated |
Download link |
| All Certbible 's Exam Dumps |
597 |
1 days ago | Available |
PassGuide Training Materials & Practice Tests
About the Author
Write a Comment
Gravatars are small images that can show your personality. You can get your gravatar for free today!

